WATER CONSERVATION PLAN
01/16/2024

Revised and updated water conservation plan (five year update)

Click HERE for report


The City of Cameron Water Update
01/16/2024
The City of Cameron will apply $23,800,000 for Water and Wastewater Utility Infrastructure. 
Read more here

Cameron Water Treatment Plant Clarifier Rehabilitation Project
01/16/2024

Project is Wholly Funded by the Drinking Water State Revolving Fund (DWSRF)
thru the Texas Water Development Board (TWDB)
Description of Project:

  • Rehabilitation of exterior and interior of concrete structures for Clarifiers No. 1 and 2 at
    the Cameron Water Treatment Plant.
  • Remove and replace existing catwalk connecting Clarifiers No. 1 and 2.
  • Removal and replacement of mechanical and electrical components for both clarifiers.
  • Connect new clarifier equipment to existing SCADA system.
  • Remove and replace existing sludge removal valve on Clarifier No. 2.
  • Remove and replace 90 linear feet of 6” recycle li