Public Notice for the
Cameron Water Distribution Improvements – Phase I
Project is Wholly Funded by the Drinking Water State Revolving Fund (DWSRF)
thru the Texas Water Development Board (TWDB)
Description of Project:
- Installation of approximately 8,922 linear feet of 2”, 4” and 6” PVC waterlines with accompanying fittings along 5 roadway corridors in the City of Cameron.
- Install approximately 25 – 4” and 6” Gate Valves by Open‐Cut, 18 – 6” and 8” Gate Valves by Hot Tap and 5 Standard Fire Hydrant Assemblies.
- Install 1,800 linear feet of PVC service lines to existing meters.
- Sawcut Existing Roadway along proposed trench and install 2‐Course Chip Seal with 12” of Crushed Limestone Base for trench width.