Public Notice for the
Cameron Water Distribution Improvements – Phase I
Project is Wholly Funded by the Drinking Water State Revolving Fund (DWSRF)
thru the Texas Water Development Board (TWDB)
Description of Project:
•Installation of approximately 8,922 linear feet of 2”, 4” and 6” PVC waterlines with accompanying fittings along 5 roadway corridors in the City of Cameron.
•Install approximately 25 – 4” and 6” Gate Valves by Open‐Cut, 18 – 6” and 8” Gate Valves by Hot Tap and 5 Standard Fire Hydrant Assemblies.
•Install 1,800 linear feet of PVC service lines to existing meters.
•Sawcut Existing Roadway along proposed trench and install 2‐Course Chip Seal with 12” of Crushed Limestone Base for trench width.